Storm Lake is drilling deeper — literally — as the city moves ahead with two new production wells designed to secure the community’s long‑term water supply.
The city council on Monday approved contracts and bonds for Well No. 23, a shallow Pleistocene‑level well that will sit on the same parcel as Well No. 22. Public Works Director Ron Covert reminded council members that crews discovered the opportunity for an additional well while drilling No. 22, making the site ideal for a second source that can share existing infrastructure.
The project carries a contract of just under $480,000, with construction and grant administration covered by a Community Development Block Grant. The well is expected to produce roughly 350 gallons per minute, feeding directly into the city’s raw water system.
The second water-related action Monday moves the city toward an even larger investment: Well No. 24, a deep Jordan Aquifer well planned for the south end of the newly acquired water treatment plant property. Covert said the site’s shape and location will help the city meet setback requirements and allow room for future water infrastructure.
He added that drilling the Jordan well will also give the city a chance to explore potential future water sources — including the Dakota Aquifer and other shallower formations.
The council approved an engineering agreement with I&S Group to design Well No. 24. The $365,000 contract is self‑funded, and the well is expected to deliver 1,250 to 1,500 gallons per minute once fully integrated into the city’s treatment system.