A massive battery storage project could be coming to Ida County — and another could follow.
MidAmerican Energy is proposing a 200-megawatt battery energy storage facility near Ida Grove, with approximately 180 to 190 large battery containers covering about 20 acres.
MidAmerican Associate Project Outreach Manager John Huff and Project Developer Ashley Taylor presented the plans to the Ida County Board of Supervisors Tuesday afternoon.
The proposed facility would sit next to MidAmerican’s Ida Grove 2 wind farm substation along Indian Avenue, near the former county landfill. MidAmerican has options to purchase 55 acres, although Huff said the battery installation would occupy less than half that land.
The system would store electricity for later use, helping balance power supply and demand when wind generation fluctuates.
Taylor explained why MidAmerican selected the location.
Before construction can begin, however, the county must establish regulations for the facility.
Board Chair Devlun Whiteing said supervisors have discussed incorporating battery storage requirements into the county’s existing wind energy ordinance, rather than adopting a separate ordinance. That approach would treat battery storage as an accessory use to a wind farm, while allowing different requirements for batteries associated with future data centers.
MidAmerican hopes to hold a public hearing on the proposed ordinance amendment in December.
Board member Creston Schubert questioned the company’s plans for fire protection, security, noise and potential impacts on nearby residents.
Taylor said the facility would use lithium iron phosphate batteries, with containers designed to prevent a fire from spreading between units. She said MidAmerican also plans to coordinate with local firefighters and develop an emergency response plan.
Another concern involved whether Ida County residents would benefit directly from the stored electricity during power outages.
Huff and Taylor said the facility could improve electrical reliability but acknowledged they had not determined exactly how the substation’s transmission connections would affect local service.
Supervisors also want answers about the project’s financial benefits.
Taylor said the facility would fall under Iowa’s utility replacement tax system, making future county revenue difficult to predict.
Schubert stressed the importance of providing that information before a public hearing.
Huff and Taylor also indicated MidAmerican could pursue a second battery storage project near another wind farm substation along Orchard Avenue, between Ida Grove and Arthur.
Supervisors expressed interest in touring an existing battery storage facility before making a decision. MidAmerican agreed to help explore that possibility.
If the necessary state and local approvals are secured, Taylor said construction on the proposed Indian Avenue facility could begin as early as July or August of next year, with operations targeted for May 2028.
Supervisors took no action Tuesday. The county plans to have its attorney review MidAmerican’s proposed ordinance changes before moving forward.