Lift Station Work On Track Despite Weather, Supply Hurdles

Storm Lake officials provided updates Monday night on an ongoing city lift station project.

City Manager Keri Navratil addressed one of the most common questions from residents—when West Third Street and College Avenue will reopen.

Concrete patching is scheduled for early next week, with traffic expected to resume mid-to-late week, depending on weather conditions.

Navratil also explained how wet soil has impacted construction schedules for the infrastructure project that is replacing an aging sewer lift station. 

She added that purchasing dry soil may be considered in the future if wet weather conditions don’t improve, and equipment delays have also been a factor.

Navratil noted that the project remains on schedule.

Share:

Girls Basketball Scores From 11-24-26

Newell-Fonda 57, MOC-Floyd Valley 49…Ellie Sievers made 4-of-9 three-pointers and scored 21 points and Quinn Sievers scored 19 points had eleven

Girls Wrestling Results From 11-24-26

Le Mars Invitational 1st-West Monona-Westwood-Whiting 228 1/2 4th-Sioux Central 126 1/2 11th-Storm Lake 58 12th-Cherokee 51 Triton Duals at Iowa Central

Local News