SL Elementary Gym Floor Contract

December 21, 2015

The Storm Lake School Board has approved the contract for the replacement of the gym floor at the elementary school.

The gym was flooded when a water main broke in June. Initially, the district thought the floor could be dried out and re-sanded… but it was reevaluated and the floor was found to be “dead.” The district’s insurance will cover the cost of replacement.

In October, the board accepted the low bid of 88-thousand dollars from Anderson-Ladd of Waukee. Work will begin as soon as school is out in the spring, and the project will be finished before school resumes next fall.