City of Storm Lake Provides Update on Lift Station Project

The Radio Park Lift Station project in Storm Lake will resume this coming Monday, July 11th.

There have been major delays in delivery of the needed equipment to make the wet well operational. Christiansen Construction is expected to mobilize equipment to the site by the end of this week.

Highway Street for Park Street to Lakeshore Drive will be closed during construction. Road closure is expected to begin the week of July 11th, and should last one to two weeks.

The lift station project is expected to be finished by the beginning of September. The project addresses the internal and external deteriorating conditions of the lift station.